Onkar Developers

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Ruko
1 of 3projects with possession moved
6 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ozarde Complex
Baramati (M Cl)
Dec 2018Dec 2018
not moved
Ozarde Residency
Baramati (M Cl)
Dec 2018Dec 2018
not moved
Apr 2024Oct 2024
6 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.