BUILDER

Navkar Developers

Type Firm / individualRERA projects 12Districts Ratnagiri, Palghar, Raigarh, Mumbai Suburban, Pune, Nashik
BUILDER THOK
Ruko
8 of 12projects with possession moved
22 moaverage extension when late
3lapsed registrations
12MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Dec 2018
not moved
Navkar City
Dahanu (M Cl) · lapsed
Dec 2019Dec 2021
24 mo
Dec 2019Dec 2021
24 mo
Sept 2020Apr 2027
79 mo
Guruji Residency
Palghar · lapsed
Dec 2023Dec 2023
lapsed
Tulsi Centre Point
Neral · lapsed
Jul 2024Jul 2024
lapsed
Jun 2025Jun 2025
not moved
Jan 2026Jul 2028
30 mo
Dec 2027Apr 2028
4 mo
Mar 2028Jul 2028
4 mo
Dec 2028Apr 2029
4 mo
Neo World
Sinnar
Dec 2030Apr 2031
4 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Navkar Mahalaxmi Enclave
P52800007452 · Khedshi
Ruko
Navkar City
P99000009015 · Dahanu (M Cl)
Ruko
Tulsi Centre Point
P52000000571 · Neral
Ruko
Shankeshwar Apartment
P51800006116 · Borivali
Ruko
Guruji Residency
P99000031100 · Palghar
Ruko
Tulsi Centre Point
P52000049922 · Neral
Ruko
Parakh Capital
P52100027484 · Haveli
Ruko
Vansh Heights
P52000049810 · Karjat
Ruko
Ipsit Anand Mangal
P51800045322 · Borivali
Pakka
Adinath Residency
P52000054955 · Roha
Pakka
Navkar City Phase I Part 14
P99000054543 · Vasai
Pakka
Neo World
P51600053929 · Sinnar
Pakka