BUILDER

Narendra Sonule & 3 Others Ramesh Sonule

Type Firm / individualRERA projects 1Districts Wardha
BUILDER THOK
Ruko
1 of 1projects with possession moved
39 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Chandan Nagar
Wardha · lapsed
Sept 2022Dec 2025
39 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Chandan Nagar
P50400026300 · Wardha
Ruko