Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Shine Square
Pimpri Chinchawad (M Corp.)
Dec 2018Dec 2019
12 mo
Shine City Phase IV
Pimpri Chinchawad (M Corp.) · lapsed
Dec 2025Dec 2025
lapsed
Dec 2029Apr 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shine Square
P52100003130 · Pimpri Chinchawad (M Corp.)
Dhyaan Do
Shine City Phase IV
P52100024175 · Pimpri Chinchawad (M Corp.)
Ruko
Shine City Phase V
P52100080761 · Haveli
Pakka