BUILDER

Naiknavarehousingdevelopementspvtltd

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Ruko
2 of 3projects with possession moved
87 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Dec 2018
not moved
Dec 2019Dec 2027
96 mo
Dwarka Project3
Mahalunge · lapsed
Dec 2019Jun 2026
78 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Dwarka Project 1
P52100000164 · Mahalunge
Ruko
Dwarka Project2
P52100000168 · Mahalunge
Ruko
Dwarka Project3
P52100000163 · Mahalunge
Ruko