BUILDER

Metro Infra

Type Firm / individualRERA projects 3Districts Thane, Raigarh, Nagpur
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
8 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Namdev Plaza
Badlapur (M Cl)
Jun 2019Jun 2019
not moved
Dec 2022Dec 2023
12 mo
Skyline Tower
Nagpur (urban)
Dec 2028Apr 2029
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Namdev Plaza
P51700003887 · Badlapur (M Cl)
Ruko
Metropolis
P52000022444 · Panvel
Dhyaan Do
Skyline Tower
P50500052872 · Nagpur (urban)
Pakka