Marigold Reality

Type Firm / individualRERA projects 2Districts Amravati
BUILDER THOK
Dhyaan Do
2 of 2projects with possession moved
20 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sumeru Vedanta
Amravati (M Corp.)
Feb 2021Oct 2021
8 mo
Sumeru Vedanta 2
Amravati (M Corp.)
May 2024Jan 2027
32 mo