BUILDER THOK
Dhyaan Do
5 of 5projects with possession moved
17 moaverage extension when late
0lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2019Dec 2020
18 mo
Dec 2021Jun 2024
30 mo
Marathon Nextown Coral
Thane (M Corp.)
Dec 2021Jun 2023
18 mo
Dec 2026Apr 2027
4 mo
Dec 2027Apr 2029
16 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Marathon Nextown Emerald
P51700000686 · Thane (M Corp.)
Dhyaan Do
Marathon Nextown Sapphire
P51700001265 · Thane (M Corp.)
Ruko
Marathon Nextown Coral
P51700000952 · Thane (M Corp.)
Dhyaan Do
Marathon Nextown Ruby
P51700021189 · Thane
Pakka
Marathon Nextown Jasper
P51700049449 · Thane
Dhyaan Do