M/S Emerald Developers

Type Firm / individualRERA projects 3Districts Raigarh, Mumbai Suburban
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
8 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Emvis Tower C
Pen (M Cl)
Oct 2022Oct 2022
not moved
Emvis Tower B
Pen (M Cl)
Apr 2024Apr 2025
12 mo
Dec 2028Apr 2029
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Emvis Tower C
P52000025984 · Pen (M Cl)
Ruko
Emvis Tower B
P52000031931 · Pen (M Cl)
Dhyaan Do
Inayah Residency
P51800034439 · Borivali
Pakka