M/s Alamdar Infrastructure PVT LTD

Type CompanyRERA projects 4Districts Mumbai City
BUILDER THOK
Dhyaan Do
3 of 4projects with possession moved
4 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ali Tower
Ward Abcd · lapsed
May 2026Sept 2026
4 mo
Marine Palace
Abcd-400002
Nov 2026Nov 2026
not moved
The Auro
Gsouth-400013
Nov 2027Mar 2028
4 mo
Nov 2029Mar 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ali Tower
P51900028809 · Ward Abcd
Ruko
Marine Palace
P51900002919 · Abcd-400002
Pakka
The Auro
P51900033823 · Gsouth-400013
Pakka
Mufaddal Park
P51900049088 · E-400010
Pakka