BUILDER

Linux Group

Type Firm / individualRERA projects 6Districts Pune
BUILDER THOK
Dhyaan Do
4 of 6projects with possession moved
8 moaverage extension when late
3lapsed registrations
6MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Viento
Mulshi · lapsed
Dec 2022Dec 2022
lapsed
Bonheur
Mulshi · lapsed
Jun 2024Jun 2024
lapsed
Jul 2024Dec 2024
5 mo
Bonheur A Wing
Mulshi · lapsed
Dec 2024Aug 2026
20 mo
Ios Prime
Mulshi
Dec 2028Apr 2029
4 mo
Dec 2029Apr 2030
4 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Viento
P52100023329 · Mulshi
Ruko
Bonheur
P52100026648 · Mulshi
Ruko
Ios Tathawade
P52100027952 · Tathwade
Pakka
Bonheur A Wing
P52100032282 · Mulshi
Ruko
Ios Prime
P52100053819 · Mulshi
Pakka
Ios Prime B1
P52100079123 · Mulshi
Pakka