BUILDER

Lakadawala Developers PVT LTD

Type CompanyRERA projects 5Districts Mumbai City, Mumbai Suburban
BUILDER THOK
Dhyaan Do
3 of 5projects with possession moved
38 moaverage extension when late
1lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Maaria Annexe
Fnorth-400037
Jan 2021Dec 2029
107 mo
Murga Giran
Mumbai City
Nov 2021Nov 2021
not moved
Centrio-by Mj Shah
Kurla · lapsed
Dec 2021Dec 2021
lapsed
Oct 2026Feb 2027
4 mo
Dec 2029Apr 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Maaria Annexe
P51900007782 · Fnorth-400037
Ruko
Murga Giran
P51900007404 · Mumbai City
Pakka
Centrio-by Mj Shah
P51800012170 · Kurla
Ruko
Centrio Nx By Mj Shah
P51800035010 · Kurla
Pakka
Lakadawala Garden
P51900077798 · Ward E
Pakka