BUILDER
Kosmos Developer
BUILDER THOK
Ruko
4 of 4projects with possession moved
28 moaverage extension when late
2lapsed registrations
4MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Signals from filings & records
2 projects lapsed on MahaRERAMahaRERA
Registration lapsed without completion being recorded.
MahaRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Vinayak Tower
P51800009164 · Borivali
Shreeyog Chsl
P51800009351 · Borivali
Nandanvan
P51800012073 · Borivali
Express Tower CHS
P51800051077 · Borivali