9 of 21projects with possession moved
14 moaverage extension when late
1lapsed registrations
21MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Dec 2018
not moved
Nov 2020Nov 2020
not moved
Nov 2020Nov 2020
not moved
Jun 2021Dec 2022
18 mo
Dec 2021Dec 2021
not moved
Dec 2021Dec 2021
not moved
Dec 2021Dec 2027
72 mo
Jun 2022Jun 2022
not moved
Dec 2022Dec 2022
not moved
Yazarina One
Fnorth-400014
Jun 2024Jun 2024
not moved
Yazarina III
Ward Fnorth
Mar 2025Mar 2025
not moved
Dec 2025Dec 2026
12 mo
Dec 2025Dec 2025
not moved
Jan 2026Jan 2026
not moved
Jun 2027Jun 2027
not moved
Dec 2027Apr 2028
4 mo
Apr 2030Aug 2030
4 mo
Apr 2030Aug 2030
4 mo
Apr 2030Aug 2030
4 mo
Dec 2030Apr 2031
4 mo
Dec 2031Apr 2032
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Rustomjee Pinnacle
P51800006915 · Borivali
Ruko
Rustomjee Paramount - Wing D
P51800000619 · Andheri
Ruko
Rustomjee Paramount - Wing E
P51800000862 · Andheri
Ruko
Eaze Zone In Laxmi Singh Complex
P51800011978 · Borivali
Ruko
Rustomjee Seasons - Wing B
P51800000605 · Andheri
Ruko
Rustomjee Seasons - Wing C
P51800000309 · Andheri
Ruko
Rustomjee Summit
P51800003590 · Borivali
Ruko
Rustomjee Paramount - Wing C
P51800000481 · Andheri
Ruko
Rustomjee Seasons - Wing A
P51800001433 · Andheri
Pakka
Yazarina One
P51900000287 · Fnorth-400014
Ruko
Yazarina III
P51900024307 · Ward Fnorth
Ruko
Rustomjee Paramount - Wing F
P51800020843 · Andheri