BUILDER

Kavita Realty

Type Firm / individualRERA projects 3Districts Palghar
BUILDER THOK
Ruko
1 of 3projects with possession moved
4 moaverage extension when late
2lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2022Jun 2022
lapsed
Dec 2025Dec 2025
lapsed
Dec 2028Apr 2029
4 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Paramount Enclave Phase 2
P99000026416 · Mahim
Ruko
Paramount Enclave Building No 6
P99000045531 · Mahim
Ruko
Sohani Heights
PR1240002502726 · Palghar
Pakka