BUILDER

Ideal Construction

Type Firm / individualRERA projects 3Districts Pune, Kolhapur
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
8 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gayatri Mantra
Pimpri Chinchawad (M Corp.) · lapsed
Mar 2020Mar 2021
12 mo
Nandanwan
Kolhapur (M Corp.)
Apr 2023Apr 2023
not moved
Dec 2027Apr 2028
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Gayatri Mantra
P52100015674 · Pimpri Chinchawad (M Corp.)
Ruko
Nandanwan
P53000020937 · Kolhapur (M Corp.)
Pakka
Manorama Sankul
P53000052199 · Karvir
Pakka