Hinjawadi Infradevelopment PVT LTD

Type CompanyRERA projects 14Districts Pune
BUILDER THOK
Dhyaan Do
5 of 14projects with possession moved
4 moaverage extension when late
4lapsed registrations
14MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2021Dec 2021
not moved
Dec 2021Dec 2021
not moved
Dec 2023Dec 2023
not moved
Dec 2023Dec 2023
lapsed
Jun 2025Jun 2025
lapsed
Jun 2025Jun 2025
lapsed
Dec 2025Dec 2025
lapsed
Dec 2025Dec 2025
not moved
Dec 2027Dec 2027
not moved
Dec 2027Apr 2028
4 mo
Dec 2027Apr 2028
4 mo
Dec 2028Apr 2029
4 mo
Jan 2029May 2029
4 mo
Jun 2030Oct 2030
4 mo

Signals from filings & records

4 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Building A2 Eon Homes
P52100006888 · Man
Ruko
Building D3 Eon Homes
P52100001860 · Man
Ruko
Building A3 Eon Homes
P52100013714 · Man
Pakka
Building D2 Eon Homes
P52100016395 · Man
Ruko
Building B1 Eon Homes
P52100026429 · Man
Ruko
Building D1 Eon Homes
P52100024680 · Man
Ruko
Building C3 Eon Homes
P52100030732 · Man
Ruko
Apostrophe Hinjawadi Tower C
P52100031595 · Man
Pakka
Apostrophe Hinjawadi Tower B
P52100048177 · Man
Pakka
Building B2 Eon Homes
P52100048176 · Man
Pakka
Building C2 Eon Homes
P52100046679 · Man
Pakka
Apostrophe Hinjawadi Tower A
P52100080628 · Mulshi
Pakka