BUILDER

Himali Construction

Type Firm / individualRERA projects 2Districts Palghar
BUILDER THOK
Ruko
2 of 2projects with possession moved
37 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ramchandra Residency Bldg No.1
Vasai-virar City (M Corp)
Jul 2018Sept 2022
50 mo
Jul 2023Jul 2025
24 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ramchandra Residency Bldg No.1
P99000010975 · Vasai-virar City (M Corp)
Ruko
Ramchandra Residency Building No. 2
P99000024898 · Kopri
Ruko