Ruko
0 of 2projects with possession moved
0 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Morya Park Phase II
Aurangabad (M Corp.)
Jun 2019Jun 2019
not moved
Moraya Park Phase III
Aurangabad (M Corp.)
Dec 2022Dec 2022
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Morya Park Phase II
P51500015005 · Aurangabad (M Corp.)
Ruko
Moraya Park Phase III
P51500017172 · Aurangabad (M Corp.)