BUILDER THOK
Ruko
3 of 4projects with possession moved
35 moaverage extension when late
3lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Hill Shire - Phase 1
Wagholi · lapsed
Dec 2019Jun 2022
30 mo
Jun 2021Jun 2023
24 mo
Guardian Anantam
Kondhwa Bk · lapsed
Dec 2022Dec 2022
lapsed
Dec 2022Apr 2027
52 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Hill Shire - Phase 1
P52100001572 · Wagholi
Ruko
Guardian Eastern Meadows - Phase 1
P52100007435 · Wagholi
Ruko
Guardian Anantam
P52100001833 · Kondhwa Bk
Ruko
Guardian Eastern Meadows - Phase 2
P52100003157 · Wagholi
Ruko