BUILDER

Grace Enterprises

Type Firm / individualRERA projects 2Districts Mumbai City
BUILDER THOK
Ruko
1 of 2projects with possession moved
24 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Bismillah SRA CHS LTD
Mumbai City · lapsed
Dec 2022Dec 2022
lapsed
Jun 2025Jun 2027
24 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Bismillah SRA CHS LTD
P51900012662 · Mumbai City
Ruko
Hussaini Park
P51900028273 · Ward E
Ruko