BUILDER

Goka Engineering Co PVT LTD

Type CompanyRERA projects 3Districts Raigarh
BUILDER THOK
Ruko
0 of 3projects with possession moved
0 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2017Dec 2017
not moved
Dec 2017Dec 2017
not moved
Dec 2025Dec 2025
lapsed

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Siddhivinayak Phase 1
P52000002530 · Warachiwadi
Ruko
Gold Valley Konkan
P52000005331 · Sanaswadi
Pakka
Gold Valley Konkan Bungalows Phase 1
P52000033944 · Mangaon
Ruko