BUILDER

Goel Ganga Space LLP

Type LLPRERA projects 4Districts Pune
BUILDER THOK
Ruko
1 of 4projects with possession moved
12 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2019Dec 2020
12 mo
Dec 2019Dec 2019
not moved
Ganga Aria A
Haveli · lapsed
Dec 2023Dec 2023
lapsed
Dec 2024Dec 2024
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ganga Aria B1 B2
P52100003739 · Dhanori
Ruko
Kamal C1 C2
P52100018318 · Dhanori
Pakka
Ganga Aria A
P52100019046 · Haveli
Ruko
Ganga Aashray
P52100029031 · Dhanori
Ruko