Type Firm / individualRERA projects 5Districts Mumbai Suburban
BUILDER THOK
Pakka
4 of 5projects with possession moved
9 moaverage extension when late
1lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Aerovista
Andheri · lapsed
Dec 2023Dec 2025
24 mo
Dec 2025Dec 2025
not moved
Aadhya
Borivali
Dec 2029Apr 2030
4 mo
The Elevate
Borivali
Apr 2031Aug 2031
4 mo
Apr 2031Aug 2031
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Aerovista
P51800012150 · Andheri
Ruko
Gagan 138
P51800033983 · Kurla
Pakka
Aadhya
P51800079135 · Borivali
Pakka
The Elevate
PM1180002600570 · Borivali
Pakka
Gagan 52
PM1180002600783 · Kurla
Pakka