BUILDER

Excel Housing

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Dhyaan Do
3 of 3projects with possession moved
27 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Excel Celestia Residency
Pimpri Chinchawad (M Corp.)
Dec 2021Dec 2023
24 mo
Excel Celestia Residency Wing B And C
Pimpri Chinchawad (M Corp.)
Dec 2022Dec 2023
12 mo
Dec 2022Oct 2026
46 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Excel Celestia Residency
P52100014266 · Pimpri Chinchawad (M Corp.)
Dhyaan Do
Excel Celestia Residency Wing B And C
P52100015436 · Pimpri Chinchawad (M Corp.)
Dhyaan Do
Excel Celestia Residency E And F And MHADA
P52100024681 · Haveli
Ruko