Type CompanyRERA projects 1Districts Mumbai City
BUILDER THOK
Ruko
1 of 1projects with possession moved
31 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Bellagio
Mumbai City · lapsed
Dec 2023Jul 2026
31 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI