Eakadanta Realtors

Type Firm / individualRERA projects 3Districts Raigarh
BUILDER THOK
Ruko
2 of 3projects with possession moved
22 moaverage extension when late
2lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2020Dec 2020
not moved
Eakadanta Sankul Phase-ii
Kondale · lapsed
Jun 2023Oct 2026
40 mo
Jun 2026Oct 2026
4 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Eakadanta Sankul Phase-i
P52000005394 · Kondale
Ruko
Eakadanta Sankul Phase-ii
P52000004401 · Kondale
Ruko
Eakadanta Sankul Phase- III
P52000004372 · Kondale
Ruko