BUILDER

Deekay Developer

Type Firm / individualRERA projects 2Districts Mumbai City
BUILDER THOK
Ruko
2 of 2projects with possession moved
17 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Deekay Solace
E-400010 · lapsed
Jul 2019Dec 2020
17 mo
Deekay Aria
Abcd-400004
Dec 2020May 2022
17 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Deekay Solace
P51900004053 · E-400010
Ruko
Deekay Aria
P51900002895 · Abcd-400004
Ruko