BUILDER

Chaitanya Suresh Kambli

Type Firm / individualRERA projects 3Districts Sindhudurg
BUILDER THOK
Ruko
2 of 3projects with possession moved
11 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ruturaj Empire
Malwan (M Cl)
May 2019Nov 2020
18 mo
Apr 2024Apr 2024
not moved
Feb 2030Jun 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ruturaj Empire
P52900006409 · Malwan (M Cl)
Ruko
Ruturaj Shashwat
P52900046554 · Malwan
Ruko
Ruturaj Aatmshree
P52900055057 · Malwan
Pakka