Ruko
1 of 4projects with possession moved
12 moaverage extension when late
4lapsed registrations
4MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Bindra Sateri Legacy C Wing And F Wing Phase I - Upto 10th Floor
Dec 2022Dec 2023Andheri · lapsed
12 mo
Dec 2023Dec 2023
lapsed
Signals from filings & records
4 projects lapsed on MahaRERAMahaRERA
Registration lapsed without completion being recorded.
MahaRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Bindra Sateri Legacy C Wing And F Wing Phase I - Upto 10th Floor
P51800017120 · Andheri
Bindra Sateri Legacy C Wing And F Wing Phase II - 11th And Above Floors
P51800025061 · Andheri
Bindra Legacy A Wing Ground , 1st To 14th And Above Floors
P51800025063 · Andheri
Sateri Legacy B Wing Phase I- 2nd And Above Floors
P51800024998 · Andheri