Type CompanyRERA projects 5Districts Pune
BUILDER THOK
Dhyaan Do
4 of 5projects with possession moved
7 moaverage extension when late
1lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Bhumi Pride
Pimpri Chinchawad (M Corp.)
Dec 2017Dec 2017
not moved
Bhumi Silveriio Phase 1
Pimpri Chinchawad (M Corp.)
Dec 2018Dec 2019
12 mo
Bhumi Silveriio Phase 2
Chikhali · lapsed
Jun 2023Dec 2023
6 mo
Dec 2026Apr 2027
4 mo
Dec 2028Apr 2029
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Bhumi Pride
P52100004657 · Pimpri Chinchawad (M Corp.)
Ruko
Bhumi Silveriio Phase 1
P52100005434 · Pimpri Chinchawad (M Corp.)
Dhyaan Do
Bhumi Silveriio Phase 2
P52100025555 · Chikhali
Ruko
Bhumi Silveriio Phase 3
P52100051295 · Haveli
Pakka
Bhumi Silveriio - Phase 4
PR1263032500910 · Haveli
Pakka