2 of 3projects with possession moved
14 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2023Dec 2023
not moved
Aug 2025Aug 2027
24 mo
Dec 2027Apr 2028
4 mo