Ashapura Developers

Type Firm / individualRERA projects 8Districts Mumbai Suburban, Raigarh, Thane, Mumbai City
BUILDER THOK
Dhyaan Do
6 of 8projects with possession moved
19 moaverage extension when late
1lapsed registrations
8MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Neelkanthdhara
Kurla · lapsed
Jun 2021Dec 2025
54 mo
Anant Corner
Bokadvira
Sept 2023Sept 2024
12 mo
Dec 2023Dec 2026
36 mo
Dec 2026Apr 2027
4 mo
Jun 2027Oct 2027
4 mo
Chheda Imperial
Ward Fnorth
Dec 2029Apr 2030
4 mo
Dec 2029Dec 2029
not moved
Dec 2030Dec 2030
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Neelkanthdhara
P51800007105 · Kurla
Ruko
Anant Corner
P52000018083 · Bokadvira
Dhyaan Do
Asha Kiran
P51700033042 · Thane
Ruko
Aditya Heights
P51700078831 · Kalyan
Pakka
Ratnadeep
P51800053957 · Kurla
Pakka
Chheda Imperial
P51900080541 · Ward Fnorth
Pakka
Hari Om Heights
PR1270002501538 · Panvel
Pakka
Hari Om Mangalam
PR1270002501291 · Uran
Pakka