BUILDER

Aryan Developers

Type Firm / individualRERA projects 6Districts Pune, Chandrapur, Thane
BUILDER THOK
Dhyaan Do
3 of 6projects with possession moved
27 moaverage extension when late
1lapsed registrations
6MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mayuri Residency
Sanaswadi (ct) · lapsed
Dec 2018Jan 2023
49 mo
Dec 2021Dec 2021
not moved
Simrah Paradise
Pune (M Corp.)
Jun 2022Jun 2022
not moved
Dec 2025Apr 2027
16 mo
Aarya One
Kalyan
Apr 2026Aug 2027
16 mo
Trillium
Haveli
Jan 2029Jan 2029
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Mayuri Residency
P52100003124 · Sanaswadi (ct)
Ruko
Aryan Appartment - 4
P50900018219 · Ballarpur
Pakka
Simrah Paradise
P52100014597 · Pune (M Corp.)
Ruko
Green Alley Phase - II
P52100049768 · Pimple Nilakh
Dhyaan Do
Aarya One
P51700050409 · Kalyan
Dhyaan Do
Trillium
P52100081088 · Haveli
Pakka