BUILDER

Ananda Developers

Type Firm / individualRERA projects 3Districts Nashik, Palghar
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
4 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Arrpan Vihar
Nashik (M Corp.)
Dec 2024Dec 2024
not moved
Jan 2027May 2027
4 mo
Advait
Nashik
Dec 2028Apr 2029
4 mo