BUILDER

Ami Buildcon

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Ruko
2 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gulmohar Pink City
Ambarnath (R) · lapsed
Jun 2023Sept 2023
3 mo
Bellevue
Ambarnath
Oct 2027Feb 2028
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Gulmohar Pink City
P51700028525 · Ambarnath (R)
Ruko
Bellevue
P51700079067 · Ambarnath
Pakka