BUILDER

Albin Anthony Cheyaden

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Ruko
2 of 2projects with possession moved
8 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Albin Developers
Kamba · lapsed
Jun 2024Jun 2025
12 mo
Jun 2028Oct 2028
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Albin Developers
P51700030834 · Kamba
Ruko
Sweet Home Luxuria
P51700053303 · Kalyan
Pakka