BUILDER

Akruti Constructions

Type Firm / individualRERA projects 2Districts Nanded, Solapur
BUILDER THOK
Ruko
0 of 2projects with possession moved
0 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kamal Residency
Nanded · lapsed
May 2026May 2026
lapsed
Akruti Heights
Solapur (M Corp.)
Nov 2026Nov 2026
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kamal Residency
P51100054294 · Nanded
Ruko
Akruti Heights
P52600023264 · Solapur (M Corp.)
Pakka