Akruti Buildcon

Type Firm / individualRERA projects 5Districts Pune, Nashik
BUILDER THOK
Ruko
1 of 5projects with possession moved
40 moaverage extension when late
2lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2018Jun 2018
not moved
Aditi Park
Baramati (M Cl)
Feb 2022Feb 2022
not moved
Akruti Heights Wing A
Nashik · lapsed
Mar 2023Jul 2026
40 mo
Audumber Residency
Haveli · lapsed
Dec 2025Dec 2025
lapsed
Aditi Park II
Baramati (M Cl)
Feb 2026Feb 2026
not moved

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Nisarg Serene
P52100002312 · Wakad
Ruko
Aditi Park
P52100015417 · Baramati (M Cl)
Ruko
Akruti Heights Wing A
P51600022925 · Nashik
Ruko
Audumber Residency
P52100049577 · Haveli
Ruko
Aditi Park II
P52100048815 · Baramati (M Cl)
Dhyaan Do