BUILDER

Aditi Builders

Type Firm / individualRERA projects 2Districts Thane, Satara
BUILDER THOK
Pakka
1 of 2projects with possession moved
4 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Hira Sadan
Ambarnath
Mar 2022Mar 2022
not moved
Jun 2028Oct 2028
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Hira Sadan
P51700023797 · Ambarnath
Pakka
Shivgad Residency
P52700027557 · Khed (ct)
Pakka