BUILDER

Ace Constructions

Type Firm / individualRERA projects 4Districts Thane, Pune
BUILDER THOK
Ruko
1 of 4projects with possession moved
37 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Falcon
Thane (M Corp.)
Jun 2018Jun 2018
not moved
Pelican
Thane (M Corp.)
Jun 2018Jun 2018
not moved
Anutham Phase 1
Hadapsar · lapsed
Dec 2021Dec 2021
lapsed
Dec 2023Jan 2027
37 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Falcon
P51700008009 · Thane (M Corp.)
Ruko
Pelican
P51700005942 · Thane (M Corp.)
Ruko
Anutham Phase 1
P52100000820 · Hadapsar
Ruko
Anutham Phase II
P52100020764 · Haveli
Ruko