BUILDER

A Plus Developers

Type Firm / individualRERA projects 3Districts Raigarh
BUILDER THOK
Ruko
1 of 3projects with possession moved
15 moaverage extension when late
2lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sept 2022Sept 2022
not moved
Golden Van
Karjat · lapsed
Mar 2025Jun 2026
15 mo
Shrusti Van
Karjat · lapsed
Mar 2025Mar 2025
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Golden Vann - Phase 4
P52000003205 · Ardhe
Ruko
Golden Van
P52000020754 · Karjat
Ruko
Shrusti Van
P52000021325 · Karjat
Ruko