BUILDER

Raj Associates

Type Firm / individualRERA projects 5Districts Amravati, Nanded, Thane, Palghar
BUILDER THOK
Ruko
1 of 4projects with possession moved
73 moaverage extension when late
1lapsed registrations
5MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Aug 2019Aug 2019
not moved
Nov 2022Dec 2028
73 mo
Aug 2025Aug 2025
not moved
Naivedya
Kalyan · lapsed
Jun 2026Jun 2026
lapsed
1 more project is being verified or has no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

4 of 5 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Raj Township
P50300011855 · Badnera
Ruko
Raj Township
P50300022183 · Badnera
Ruko
Bharadiya Tower
P51100050694 · Nanded
Ruko
Naivedya
P51700052399 · Kalyan
Ruko
Subway Residency
P99000010520 · Vasai-virar City (M Corp)
Not scored