BUILDER

Mahadev Developers

Type Firm / individualRERA projects 3Districts Kolhapur, Thane, Nashik
BUILDER THOK
Dhyaan Do
2 of 3projects with possession moved
10 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2025Dec 2025
not moved
Belpatra
Bhiwandi
May 2026Sept 2027
16 mo
Jun 2028Oct 2028
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Naik Kharude Heights
P53000051048 · Ajra
Dhyaan Do
Belpatra
P51700053122 · Bhiwandi
Dhyaan Do
Samarth Anex
P51600053622 · Nashik
Pakka